Optimisation of dragline inspection intervals with time-counter algorithm

International Journal of Mining, Reclamation and Environment

YÖKSİS OpenAlex SJR Q2 JCR Q3 Citations 11 Percentile 82.9% FWCI 1.7
Year
2017
ISSN
1748-0930
Type
article

Data source split

  • YÖKSİS YÖKSİS article record
  • OpenAlex OpenAlex enrichment (abstract, citations, topics)

Abstract

English (OpenAlex)

This research study proposed a novel algorithm, called time-counter, to optimise inspection intervals of production systems. The developed algorithm was applied to two active draglines. The algorithm evaluated random uptime/downtime characteristics of the draglines and the planned dragline halts in the mine. Physical and random non-physical costs were included and annual maintenance cost minimisation was achieved. Dragline-1 and Dragline-2 inspection intervals were optimised as 232 and 184 h and their maintenance costs were reduced by 5.9 and 6.2% compared to the current interval, respectively. This study is the first initiative in cost-effective inspection interval optimisation of a mining machinery.

Topics

  • Reliability and Maintenance Optimization
  • Mining Techniques and Economics
  • Risk and Safety Analysis

Primary topic Reliability and Maintenance Optimization