Approximate Estimation of Man-Day in Ship Block Production: A Two-Stage Stochastic Program
Veri kaynağı ayrımı
- YÖKSİSYÖKSİS makale kaydı
- YÖKSİS dergi adıPolish Maritime Research
- Katalog eşleşmesi (ISSN)Polish Maritime Research
- OpenAlexOpenAlex zenginleştirmesi (özet, atıf, konular)
- Semantic Scholaratıf sayısı (OpenAlex ile birleştirilmez)
Özet
Abstract It is critical to estimate the workforce requirements for the production of blocks in shipbuilding. In this study, the number of workforce (man-day) required for the production of a passenger ship’s double bottom block was estimated. Initially, the production of the block was observed, and the average working performance of the mounting, welding, and grinding workers was recorded. Block drawings were examined and the work required was calculated. The amount of work increased, depending on any revisions required due to incorrect or incomplete designs. The average working performance of an employee is uncertain due to environmental factors, including the weather and working conditions, as well as health (both physical and mental). A two-stage stochastic programming model with recourse was established to estimate man-day required and a Sample Average Approximation (SAA) technique was used to obtain a near-optimum solution. The results of the study were compared with shipyard records and an agreement of approximately 90% was achieved.
Konular
Atıflar
OpenAlex cited_by_count. WoS veya Scopus atıf sayısı değildir; o kaynaklar için ayrı kolon yoktur.
3atıfOpenAlex · cited_by_count (önbellek / veritabanı)
Yerel katalogda bu makaleye atıf yapan 5 yayın (OpenAlex referans eşleşmesi; tam dünya listesi değildir).
- 2025 Examining a multi-skilled project scheduling problem for shipyard industry through operational and tactical perspectivesAtıf 2 · OpenAlex
- 2025 Examining a multi-skilled project scheduling problem for shipyard industry through operational and tactical perspectivesAtıf 2 · OpenAlex
- 2026 Workforce Planning for HDPE Boatbuilding Using Two-Stage Stochastic Programming ModelAtıf 0 · OpenAlex
- 2026 Workforce Planning for HDPE Boatbuilding Using Two-Stage Stochastic Programming ModelAtıf 0 · OpenAlex
- 2026 Workforce Planning for HDPE Boatbuilding Using Two-Stage Stochastic Programming ModelAtıf 0 · OpenAlex